Archive for August 6th, 2010

Measuring encoder fits shafts to 2 m

Measuring encoder fits shafts to 2 m

A modular steel tape rotary encoder is available for shafts with diameters from 6 in. (150 mm) to 6 ft (~2 m). Applications for the MSR 40, an economical ring encoder, include rotary tables and turbine shafts. The steel tape of the MSR 40 uses the Single-Field Scanning principle with 200µm grating pitch – offering ease of mounting and high angular resolution. System accuracy is ±30 µm/m with an operating temperature of 0 to +50° C. The encoder can work at high speeds, especially for large measurement applications. A clever feature of the MSR 40 encoder is that it links the ends of a steel tape together with one of two joining mechanisms. This makes it possible to measure through a full 360°. Another version (MOR) uses a steel-ring-tensioning cleat for encoders mounted to a steel surface thus allowing for thermal expansion. The MER version uses a rubber gasket with a low-profile tensioning cleat for other mounting surfaces. Depending on shaft diameter, line counts of up to 20,000 are available on the MSR 40. All versions offer quasiabsolute positioning by distance-coded reference marks or homing by a single reference mark. The MSR 40 mounts easily and comes in standard and custom sizes.

RSF Elektronik

heidenhain.com


Visit the original post at: Wind Power News

Engineering the floating wind farm

Engineering the floating wind farm

There seems no shortage of creative thinking for placing turbines offshore. Take the Hexicon Energy Platform for example. The concept comes from Sweden-based Hexicon AB, (hexicon.eu) and shows the culmination of several clever ideas for generating power from wind and waves. The design is said to reduce service needs and extend its lifespan thanks to a platform equipped with a Fagerdala Hull. It’s a sandwich of dense foam between steel plates that will need no painting, and so provide a longer life of equipment and structure. The firm says the floating platform with this hull can:

The Hexicon Energy Platform in this configuration will span 360-m across, and larger units are possible. The structure is based on a hull design made of sandwiched materials that provide a formable yet rigid structure. The orange crane to the left runs around the perimeter on rails and is carrying a blade for an unfinished turbine.

• House most of today’s wave, wind, and ocean-current energy generators

• Upgrade easily to more advanced turbines or ideas

• Assemble and be equipped on location

• Require less maintenance than conventional ocean structures

• Be attractive, mobile, and flexible

• Include equipment to manage harsh weather

• Provide a relatively short ROI

The firm says the unit can be constructed in sections, shipped to location or nearby port, and assembled there. The design can be built in many more locations and in deep water that would rule out conventional seabed foundations. A configuration with a 360-m dia., says Hexicon, could have an energy generation capacity of 30 to 60 MW or more depending on development, location, and equipment. The platform is large enough to carry more than wind turbines which will improve its overall power output. For instance, a recent idea is to generate energy from wave and ocean-currents.

Up and down wave action provide the possibility of capturing wave energy.

The company says comparing the cost/kWh produced to stationary offshore single-mounted units shows a competitive edge. The cost of maintenance, service, turbine repair, gearboxes, and other equipment will be reduced because the hull protects the platform and equipment. The Hexicon platform is large enough to support and carry out work on board with an onboard crane and a crew available 24/7. The crew will be able to perform its duties with little regard to weather and hence will have little need of service ships.

A cross section of the perimeter structure shows how waves would be directed over it and down in a way that captures some of their kinetic energy. The circular center sections, about 8-ft dia., lets crews walk around to service equipment.

An anchoring method lets the platform always face the wind. In case of hurricane-force winds or ice buildup, the platform can be lowered or raised with ballast. This means locations with active ocean currents or tidal currents, such as the Gulfsteam, can also provide a constant source of power.

The platform is said to be large enough to withstand harsh weather and still offer comfortable working and living conditions. Hexicon also claims easier logistics. For instance, mounting or removing turbine blades needs no service ship. Onboard rails guide a mobile crane around the perimeter along with other equipment to handle heavy turbine components. WPE


Visit the original post at: Wind Power News

Engineering the floating wind farm

Engineering the floating wind farm

There seems no shortage of creative thinking for placing turbines offshore. Take the Hexicon Energy Platform for example. The concept comes from Sweden-based Hexicon AB, (hexicon.eu) and shows the culmination of several clever ideas for generating power from wind and waves. The design is said to reduce service needs and extend its lifespan thanks to a platform equipped with a Fagerdala Hull. It’s a sandwich of dense foam between steel plates that will need no painting, and so provide a longer life of equipment and structure. The firm says the floating platform with this hull can:

The Hexicon Energy Platform in this configuration will span 360-m across, and larger units are possible. The structure is based on a hull design made of sandwiched materials that provide a formable yet rigid structure. The orange crane to the left runs around the perimeter on rails and is carrying a blade for an unfinished turbine.

• House most of today’s wave, wind, and ocean-current energy generators

• Upgrade easily to more advanced turbines or ideas

• Assemble and be equipped on location

• Require less maintenance than conventional ocean structures

• Be attractive, mobile, and flexible

• Include equipment to manage harsh weather

• Provide a relatively short ROI

The firm says the unit can be constructed in sections, shipped to location or nearby port, and assembled there. The design can be built in many more locations and in deep water that would rule out conventional seabed foundations. A configuration with a 360-m dia., says Hexicon, could have an energy generation capacity of 30 to 60 MW or more depending on development, location, and equipment. The platform is large enough to carry more than wind turbines which will improve its overall power output. For instance, a recent idea is to generate energy from wave and ocean-currents.

Up and down wave action provide the possibility of capturing wave energy.

The company says comparing the cost/kWh produced to stationary offshore single-mounted units shows a competitive edge. The cost of maintenance, service, turbine repair, gearboxes, and other equipment will be reduced because the hull protects the platform and equipment. The Hexicon platform is large enough to support and carry out work on board with an onboard crane and a crew available 24/7. The crew will be able to perform its duties with little regard to weather and hence will have little need of service ships.

A cross section of the perimeter structure shows how waves would be directed over it and down in a way that captures some of their kinetic energy. The circular center sections, about 8-ft dia., lets crews walk around to service equipment.

An anchoring method lets the platform always face the wind. In case of hurricane-force winds or ice buildup, the platform can be lowered or raised with ballast. This means locations with active ocean currents or tidal currents, such as the Gulfsteam, can also provide a constant source of power.

The platform is said to be large enough to withstand harsh weather and still offer comfortable working and living conditions. Hexicon also claims easier logistics. For instance, mounting or removing turbine blades needs no service ship. Onboard rails guide a mobile crane around the perimeter along with other equipment to handle heavy turbine components. WPE


Visit the original post at: Wind Power News

Ceramic coating shields generator bearing

In an electric environment, electrolytic corrosion from stray currents threatens bearing performance. NTN’s coated angular contact ball and cylindrical roller bearings, the MEGAOHM Series, insulate the bearings from electric current. A special ceramic coating applied to the outer surface and side faces of the outer ring prevents current from passing though the bearing. The design provides an insulation resistance of at least 2,000 M?. Under normal operating temperatures, this alleviates electrical arcing and early failure. The bearings come with or without seals or shields, and are interchangeable with standard, non-insulated bearings. Features and benefits of the series include being OEM preferred, they come in ball and cylindrical roller bearings, and they come with extensive OEM experience and service history. The bearings are available with bores of 50 to 160-mm dia. Options include specialized quality inspections with individual bearing serial numbering. The units follow GL Guidelines.

NTN Bearings www.ntnamerica.com


Visit the original post at: Wind Power News

Top 10 best practices for avoiding construction change orders

Although change orders are not always a bad thing, site developers and construction companies have formulated a few guidelines for minimizing them.

By: Paul Dvorak/Editor

The blades are about to go on a turbine at the Gulf Wind project built by RES Americas. The company says projects stay on schedule when trusted crews are assembled before breaking ground.

Contract change orders are so ubiquitous in some industries that if you Google the term, spaghetti-like flow charts pop up showing how a few organizations handle the changes. The charts are mostly from state organizations and aimed at road construction companies.

Change orders are often requests subcontractors present to site developers because of unanticipated conditions usually in the soil or scheduling. The general impression is that change orders are from oversights or embarrassing mistakes. But that is not always the case, say the people we interviewed. Wind farms are considerably different from general road and construction jobs because so much is influenced by their remoteness, large and complex schedules, and that coveted PPA.

Where do they come from? The first wind farm finished many projects ago, so why do change orders still crop up? There are many reasons, but our sources focused on these:

It’s the roads. “From our experience, it’s the roads and the reason is that they cover a large part of the construction work in wind projects,” says Blair Loftis, Kleinfelder Engineering’s VP and national director of alternative and renewable energy. “A turbine site might occupy only a quarter acre, but you can have many miles of roads for construction access and permanent use.”

Scheduling errors. “We’ve had only two noteworthy change orders on wind projects in the last 12 years and both involved late supply of wind turbines,” says Andrew Fowler, Executive VP of Construction with RES Americas. “Both occasions involved the late delivery of turbines due to new facilities and technology. The first occasion was from issues at the new turbine factory and the second was due to the slow delivery of a brand new turbine model,” says Fowler. “RES Americas has a successful record of BOP construction projects, but obviously, if the delivery of the turbines is delayed, the impact on the construction schedule can be significant. If a turbine design is new or the turbines are being shipped a long distance, that can affect delivery in a bad way.”

In addition, each state DOT has different rules on width, length, and divisible roads. Some states, for instance, let trucks piggyback two components, two blades or a blade and a hub. Other states insist that if such a load can be divided, then it’s an oversized load, and must be divided into two.

What’s more, truck loads may be fine when they leave the factory. But when they come to a border, they may have to go far to the east before heading west because one state on a more direct route says the truck isn’t loaded properly.

Remote locations: When equipment companies deliver machinery to conventional locations, they go to an address on a paved road most drivers can easily find. But when delivering turbines to a wind farm, the “address” is a dirt road in a corn field that looks like every other corn field in the country. To make matters worse, components are coming from all points on the compass and they must arrive in a four-hour window. That kind of precision invites delays.

Hurry, get the power purchase agreement: Owners are trying to get their power to market quickly and do what they can to limit the capital put forth in early design stages. “They have to put enough capitol up front to acquire the purchase agreement or PPA, and to do that they must move forward to final construction stages,” says Kleinfelder’s Loftis. But most planning for the pro forma is done off of limited engineering. For instance an owner may only take the project up to 60% of engineering design to secure the PPA because that gives the project financial legs. That PPA comes with a hard date to get the project grid connected. Hence, rushing and risks.”

Owners will take risks to cut costs. “Change orders are not always bad,” says David Hattery, a partner with Seattle-based law firm Stoel Rives LLC. Hattery has 20 years of legal experience with energy construction projects. “Change orders can be good for a project because they may lead to lower costs. The insinuation some make is that something sinister or bad has happened. The reality is that, change orders merely deal with unanticipated situations. A lot of what goes into a contract is the allocation of risk.”

A tower foundation provides a simple example. “A contractor may assume in its bid price that the foundations will be built in good soil based on the owner’s soil report,” says Hattery. “If the contractor starts work and finds something not shown in that report, say, hard rock, which is more expensive to deal with, then that will call for a different foundation and a redesign. If a contract makes the contractor responsible for these extra costs, then it will reasonably increase its bid price to cover the risk of encountering rock, pocketing the difference if no rock is encountered. However, if the contractor knows that it will get a change order if it runs into rock, it will price the foundations for the less expensive foundation, and the owner will only pay the extra costs if and when the foundations hit rock. This results in a fairer price and a more efficient project overall.

A few best practices. For construction firms, detailed plans are one way to avoid change orders. “Ideally, everyone will have their engineering correct at the beginning of the project,” says RES Americas’ Fowler. “It’s important to have the construction team involved in the development phase. That way, development benefits from the experience of the construction team and construction is able to better plan its work with a better understanding of the entire project.” But the ideal is infrequently encountered, so our experts suggest these best practices for avoiding construction change orders.

Best practice 1: Get subcontractors involved as early as possible. All contributors agree that the secret, if it’s a secret, is to get everyone onboard early on. “Having everyone working from the same plan at the outset makes it easier to iron out wrinkles before construction commences. That let us avoid change orders,” says Fowler.

Others concur. “We normally know about a project six months to a year in advance,” says Kleinfelder’s Loftis. “That’s when we start working with owners in a controlled format looking for encumbrances and constraint issues that can be built into an evaluation. And if not, the issues can be raised and contingencies planned.

Loftis says a few early questions to ask include: How much of the real-estate is available for wind development? Can we anticipate intervening concerns? What issues surround habitat or jurisdictional delineations? What about the community or stake holders that may intervene and want some land conveyance? There may be some specific creature, flora or fauna, relevant to that region. “Working with owners early in a consulting approach lets us anticipate these things so they are not surprises,” he says.

Best practice 2: Walk the site. Surprisingly, some projects are bid sight unseen, in engineering terms, says Kleinfleder’s Loftis. “Bidders will look at photo imagery. Google is sufficiently advanced for that, after which they will put together an order-of-magnitude bid. You really have to get out there, look at the site, and see what the constraints may be and what conditions vary across the site. There is no substitute for putting boots on the ground. Otherwise, bidders make gross generalizations. We often go out with the developer and a team that includes a representative from the construction company, the site’s geotechnical engineer, its meteorologist for wind resources, the site’s biologist, and the civil design engineer. The team approach is to look at the site and evaluate the issues to incorporate into the plan, the scope, and ultimately, the cost.”

Also, look at alternative surveys, any sort of exhibit from the developer. This information will assist in developing a useful field exercise, a site walk or reconnaissance.

Best practice 3: Thoroughly review the contract to alleviate risk. Just as you walk the site, “walk” the contract. “Identify the project areas you think are going to be problems and spend your powder there,” says Stoel Rives’ Hattery. As the industry grows, it moves toward standardization, even though every project differs. Hattery suggests several questions in a contract review. For instance, how remote is the site? A lot of project work involves moving large equipment. A lot of it on rough roads that are fairly dicey, and in windy places. “Every site will have a different challenge be it roads, weather, or rain,” he says.

“In this practice, you literally read through each and every contract clause and think: What’s different about this project? Talk to developers and owners. The question I like asking is: ‘What do you think is going to be the problem?’ Engineers know this. Are they worried about a tight schedule? Worried about the turbines being delivered all at once or about crane availability? Are they worried about not getting the A-team from a particular contractor?” says Hattery.

Best practice 4: Write your preferences into the contract.Ask for key people, those you trust, and write their names into the contract, says Hattery. “The last thing to worry about is getting inexperienced crews. As contract director, you can go into all levels of detail.”

Best practice 5: Let the BOP contractor supply the turbines.“This gives the contractor responsibility for coordinating turbine delivery so the units arrive when they are ready to be lifted,” says Fowler. “On the two occasions I mentioned when we did encounter significant delays due to the late delivery of turbines, we had big cranes on site just waiting, for six months in one case and nine months in the other. That is a long time for any construction project to be on hold, and like any industry, delays cost money. A contractor in control of the turbine supplier would have total responsibility to short out the issues.”

Best practice 6: Keep the bidding competitive.“This is important for strategic reasons,” says Fowler. “If someone comes in way under two or three bids that you know are about right, then you have be careful.” A bid of 20 or 30% less than the budget should be a red flag.

Hence, it is always a good idea to keep bidding competitive. “There is always someone else lined up for the next project. Aligning yourself with multiple trusted partners puts you in a stronger position. If you have just one company bidding some aspect of a

project, then it is more difficult to spot issues as you have no comp-arison and are in a far weaker position to fix the problem when you find them.”

Fowler admits that his advice comes from events that occurred two years ago when conditions were different than they are today. “For example, a lot of projects were moving forward, but there was a shortage of turbines. Consequently, companies were ordering turbines a couple of years in advance. Things have changed a lot since then. One big difference is that the supply of turbines has increased, so people need not order too far ahead and turbine suppliers need not be on critical path with different projects competing for the same production slot.”

Best practice 7: Use face-to-face conferences to find problems.“I’m a big advocate of, at some point, sitting down with the project team in a face-to-face meeting,” says Stoel Rives’ Hattery. “Only so much can be done on the phone, so at some point you need to sit down in a quiet room, turn off the cell phones, and think about the project, the site plan, and carefully consider the appropriate allocation of risk for this specific project. As a gatherer of issues, I’ll try to get those risk points clearly covered in the contract. I’m very respectful of the professional developers and engineers. They know what they are doing,” he says.
Hattery suggests a few titles to invite. “If we represent owners, as we do more often than we do contractors, there will be a key leader or project developer, and they will also bring in an outside engineering firm or two. and a project developer who is responsible for things such as permit siting. A director of construction often comes into a project after development has progressed to a point where construction is the issue and they really put in the details. Those are the people you want because their issues converge,” he says.

Best practice 8: Work on clear communications and good relationships. Good relationships should link the owner, contractor, and equipment vendor. Make sure the subcontractor is able to complete its tasks on time. “If bidding out to subcontractors, use people you have used before and you like. They are more likely to understand the requirements and give you a better idea of what real costs should be,” says Fowler.

“Include the OEMs because they typically come on site and commission their turbines,” says Hattery. The turbine OEMs will deliver, but the BOP contractor mechanically completes the equipment. “The contractor and OEM will walk through each turbine and say this is mechanically complete after which the OEM representative will commission the turbine. The better those people talk to each other, respect each other, and believe that one is not trying to get into the other’s pocket, the more smoothly the project flows.

Lawyers will spend a lot of time on how turbines will be considered mechanically complete. “I want an agreed checklist so that the owner, the BOP contractor, and OEM are all on the same page,” says Hattery.
In addition, these details should be clearly listed in a document for all significant parties. “Then everyone can stay in their lanes, they know what to do, and have a clear expectation that if something is not done, it’s on their watch. If it’s on someone else’s watch, we know it too,” he adds.

Best practice 9: Update the project checklists as the industry changes. Each project will probably require several checklists before the final walk-through. The box, Change orders for late bolts, tells of seemingly inconspicuous items that are absolutely essential but were overlooked until they were needed.

Bake the details of a checklist into the contract, says Hattery. Most such checklists are proprietary and everyone has a little different way of going about them, but such lists can be points of negotiation. “There is a confluence of three interest here,” says Hattery. “It’s where to interface with a construction guy from the developer’s side, with the contractor’s project manager, and the turbine manufacturer.”

One construction firm tells of a distribution to which it sends its most recent compilation of lessons learned from the previous job. The list goes to subcontractors, suppliers, staff, and supervisors from the project. And the firm expects its subs to implement the lessons.

The firm also builds the lessons learned into preconstruction planning meetings that are reviewed
for follow-on projects. Checklists of this sort can approach 100 items and includes lines for sales tags, labor relations, community relations, to engineering check-offs and budgets.
And don’t wait for subcontractors to ask for copies of the list. Send it to them and expect to see its ideas in their next proposal.

Although the Gantt chart is fairly simple, it reflects micrositing of turbines through civil design and preparation of bid specifications for the EPC contractor. This is where a project’s design phase requires most effort. Total duration is about six months. Kleinfelder’s Blair Loftis says planning of this sort has won projects for his company.

Best practice 10: Put the schedule on a Gantt chart and share it. A Gantt chart is a schedule of interdepend-ent tasks, predecessors, a critical path, leading and lagging events, milestones, resource loading all of which require buy-in. Loftis suggests several scenarios and how they might play out guided by a Gantt chart.

“A Gantt chart can be overlaid with the construction schedule and so let teams head off conflicts. For instance, suppose someone suggests finishing the geo-technical work in a month. The chart might indicate the task as doable if that team runs four crews instead of two, and at an additional cost.”

Another scenario might show need for an 80% complete civil design because a category supervisor has to review it before getting building permits. “Suppose the 80% mark must be reached by December while the Gantt chart shows the work not done until March, then you can respond with a need for more resources to accelerate work and request additional costs. Go through this approach so teams understand the interconnections between scope, schedule, and budgets,” says Loftis.

The design gets buy-in this way. “The final thing we do is assign a qualified project manager, whose only role in the project is to manage the iron triangle – scope, schedule, and budget. Every project needs someone accountable for making sure things stay within the bounds of the triangle,” he adds.

So change orders are not always some-thing bad, they are just part of contract administration. There are often no-cost changes, and occasionally they are deductive cost changes. Sometimes prices go down. “We’ve seen projects with dozens of change orders, and that does not mean there are bad things going on,” says Hattery. “It can mean that the parties are on top of all the little changes and people are being careful contract administrations. And then there are projects with few change orders but huge problems and law suits. So, the two things do not necessarily correlate.”

Fowler says his goal is always zero change orders to the client, something his company has delivered more than once in the past few years. “In cases where we had a few from subcontractors, we handled them in a way that resulted in none to clients. It’s how you get repeat business.” And this business, some say, is all about repeat business. WPE


Visit the original post at: Wind Power News

2009 U.S. Wind Technologies Market Report summarized

Earlier today the Lawrence Berkley National Laboratory released its’ 2009 Wind Technologies Market Report, which gives a fairly detailed description of the wind industry to date, as well as points out some key characteristics and data from 2009. As I was reading through the information, looking at all the graphs, and taking in the different charts, I couldn’t help but think about the tremendous growth the U.S. is encountering and the even more phenomenal growth that lies ahead.

According to this report, wind power installations in 2009 reached roughly 10,000 MW and accounted for over $21 billion invested. This investment from investor owned utilities (IOU’s), venture capitalists, and local public utilities amounts to a new national record for installed annual wind power; a record that is 20% higher than its predecessor. Now, as we think about this number and the fact that the wind industry is growing faster and stronger than ever before, we also need to take into account what that number means relative to our nations total power portfolio.

To give some reference, at the end of 2009, the cumulative wind power capacity in the United States was just over 35,000 MW. This is about 35% more than the next country in installed capacity, China at 25,853 MW with Germany close behind at 25,813 MW. Now several countries are starting to achieve relatively high levels of wind power penetration in their electricity grids with Denmark leading the pack at roughly 20%. Following Denmark is Spain at 14%, Ireland at 11%, Germany at 8%, and the point that really astounded me… the U.S. at only 2.5%.

Now I don’t know about you, but with all the chatter about how the U.S. leads the world in installed wind capacity and how we’ve been a leader in new annual installations for four years in a row, I was beginning to think that we might at least be making a dent in the overall energy portfolio. But, alas, we are not. However, for those of us involved in the wind industry, this is good news. With 29 states plus the District of Columbia implementing renewable portfolio standards that far exceed 2.5%, our government and our policy-makers are priming the country for some extreme growth in the next few years. I guess that would explain the attraction the worlds top turbine OEM’s have to the U.S. with 7 of 10 top OEM’s currently producing domestically and 2 with concrete plans to produce domestically.

What are your thoughts? Is the industry primed for extreme growth, or will the demise of the tax credits and grants in 2013 cripple the industry for the foreseeable future?

2009 Wind Technologies Market Report
2009 Wind Technologies Market Report Executive Summary


Visit the original post at: Wind Power News

Solar Panel Placement

Solar Panel Placement

Here’s a quick and nifty little Q & A about placing solar panels on residential rooftops. In this case a a planned shop being built on a property has had an electrical easement. The building will have to be rebuilt on a different part of the property that may not be as suitable for having rooftop solar panels.

The answer is finding optimal alignment for the panels according to your location:

Check out How to Get Maximum Solar Energy Collection.


Visit the original post at: Solar Power News

K2pure and Ballard Use Bleach Manufacturing Waste to Produce Hydrogen

Back in December 2007, I talked about how two chemical companies in Canada were starting to capture the waste hydrogen when producing sodium chlorate. The H2 they had simply been burning off was enough to provide hydrogen fuel to 20,000 cars.

Now, another chemical plant is making a conversion so that it uses its hydrogen by-product rather than simply burning it off. The K2 Pure Solutions bleach plant in Pittsburg, California has teamed up with Ballard’s CLEARgen fuel cell system to use the waste hydrogen from producing bleach to create electricity for the plant.

In the past I’ve also talked about manufacturers such as breweries, wineries and candy makers turning their waste products into hydrogen that can either be sold on the open market for cars or used internally to power their facilities.

But, the chemical companies that are already producing hydrogen as a waste by-product and simply burning it off are a huge untapped market that makes sense economically and environmentally. Economically and environmentally the hydrogen can either be sold on the open market for cars that will reduce smog or used to replace some of their current electrical needs and replace energy generated from presumably nearby fossil fuel burning power plants.

Since some hydrogen car critics think that the only methods to produce hydrogen is through steam reforming of natural gas or electrolysis of water I would like to offer this as another alternative that has a potential far from being realized right now. Chemical companies that product hydrogen as a by-product and simply waste it need to be dealt with on a larger scale for their own economic benefits and our environmental benefits.


Visit the original post at: Fuel Cell News

Renewables & efficiency – Aug 6

Renewables & efficiency – Aug 6

-Fossil fuel subsidies are 10 times those of renewables, figures show
-Scaling Up Solar: The Global Implications of a New Study that Says Solar Power Is Cost Competitive with Nuclear Power
-Free solar panels and cheaper bill offered in exchange for use of roof by electricity firm
-Unity College Gives Solar Panels From Carter White House to China

read more


Visit the original post at: Energy News

Water Stocks News; Upgraded Design of Wescorp’s (OTCBB:WSCE) Mobile H2Omaxx Unit Increases Capacity to 10,000 Barrels Per Day
CALGARY, ALBERTA – August 6, 2010 (Investorideas.com Water Stocks Newswire) – Wescorp Energy Inc. (OTC.BB:WSCE), a clean water technology company focused on implementing its low-cost solutions into several markets


Visit the original post at: Energy News

Solar Stocks; MoneyTV with Donald Baillargeon, 8/6
LOS ANGELES, CA – August 6, 2010 (Investorideas.com renewable energy/green newswire) – Solar thin-film technology, sterilization, green energy upgrades, Nevada gold


Visit the original post at: Energy News

OTC Volume Leader Biotech Stocks and Green EnergyStocks; OTCVolumeLeaders.com; Most Active ($0.14-$0.25): (OTCBB: HDVY), (OTCBB: GHLV), (OTCBB: OOIL), (OTCBB: WNDT)
Point Roberts, WA (Investorideas.com Newswire) August 6, 2010 – OTC VOLUME LEADERS reports on the most active trading stocks on the OTCBB.


Visit the original post at: Energy News

ODAC Newsletter – Aug 6

ODAC Newsletter – Aug 6

There was an almost audible sigh of relief this week in the US as BP and the White House proclaimed the ‘static kill’ procedure on the Macondo oil well a success. With elections approaching the Obama administration will be keen to draw a line under the oil spill and focus on other issues, as reflected by a surprisingly upbeat press conference on Wednesday in which officials announced not only the plugging of the well but also the apparent disappearance of 75% of the spilled oil…

read more


Visit the original post at: Energy News

ODAC Newsletter – Aug 6

ODAC Newsletter – Aug 6

There was an almost audible sigh of relief this week in the US as BP and the White House proclaimed the ‘static kill’ procedure on the Macondo oil well a success. With elections approaching the Obama administration will be keen to draw a line under the oil spill and focus on other issues, as reflected by a surprisingly upbeat press conference on Wednesday in which officials announced not only the plugging of the well but also the apparent disappearance of 75% of the spilled oil…

read more


Visit the original post at: Energy News